Building the Future



Mariposa Hall
Your 2004 Bond Dollars at Work
In spring 2008, the Maricopa Community Colleges Governing Board awarded Orcutt / Winslow Partnership and McGough Construction the contract to design and build a new learning studio classroom complex at Estrella Mountain Community College. This state of the art LEED certified facility allows the college to provide West Valley citizens increased access to education, job training and technology. Mariposa Hall, the fourth capital project as a result of Prop 401, is tentatively scheduled to open for classes in spring 2010. .



Timeline:


November 2004
Voters pass Prop 401 - Maricopa Community Colleges $951M Bond Request
- $71M allocated for Estrella Mountain

March 2007
Maricopa Community Colleges Governing Board approves second round of bond sales - $240M in General Obligation Bonds

Spring 2008
Orcutt / Winslow and McGough Construction are awarded contract to design and build new classroom complex at Estrella Mountain

Spring 2009
Mariposa Hall construction scheduled to begin

Spring 2010
Mariposa Hall scheduled to open


Mariposa Hall ARCHITECTURAL Rendering | May 2008 orcutt | winslow



Highlights - Mariposa Hall

  • More than 22,000 gross sq. feet

  • Ten multipurpose learning
    studio classrooms

  • Ten faculty offices

  • Two nursing labs and one
    multipurpose lab

  • Seamless architectural and
    technology integration

Highlights - SouthWest Skill Center Remodel

  • Creation of two Emergency
    Medical Technician labs

  • Medical Assistant Lab - remodel

  • New paint and flooring
    throughout the building

  • Upgraded security features

  • Signage